  • Customer:ENTREPOSE PROJETS S.A.S. www.entrepose.fr
  • Year:2015-2017
  • Quantity:4 sets of process platforms
  • Guration:Main platform, mezzanine, vertical pipe rack, platforms and such structures as stairs, gangways, secondary platforms
  • Total weight:5766 ton

Back to projects

Manufacture of module steel structures of the SP38 work package for 4 off LNG tanks of the Yamal LNG Project for Integrated Development of South-Tambey Gas-Condensate Field

In 2017, OOO Kliver has become the unique company in Russia having experience in the turn-key manufacture of process modules for the Yamal LNG project, the largest integrated project in Russia for production, liquefaction and delivery of natural gas.

The platforms were constructed as complete, fully outfitted modules minimizing assembly activities in harsh weather conditions.

Along with the manufacture of stainless steel process piping systems with an operating temperature of -160 °C, the scope of work also included installation of trace heating, instrumentation, application of fireproofing and cryogenic spill protection coating, installation of insulation and application of corrosion protection coating.

Completed platforms were shipped through the Baltic Sea, North Sea, Norwegian Sea, Barents Sea and the Kara Sea to the port of Sabetta on the Yamal peninsula.

OOO Kliver executed the project in cooperation with the leading Russian and foreign vendors and subcontractors. Technical support of the construction process and quality control were carried out in close cooperation with specialists of ENTREPOSE PROJETS S.A.S.